Following a four-month pause due to weather conditions, our Ævia teams have launched the ultimate phase of the bridge's waterproofing renewal.
To date, 10,000 m² of this iconic structure have been fully rehabilitated. The project now focuses on the remaining 3,000 m² to preserve and ensure the long-term durability of this exceptional asset.
This major undertaking is being executed with rigor and commitment under significant operational constraints, driven by a clear objective: to meet strict deadlines while minimizing disruption for users.
Congratulations to all our mobilized teams for their professionalism and dedication!
Credit: Olivier Sergent - Sernavision
-
12.06.2026Inauguration of the new site facilities for the EPR2...The project's site facilities were inaugurated yesterday by Xavier Mony and Christophe Sandré, in the presence of Audrey Baconnais-Rosez, Sub-prefect of Dieppe;... -
09.06.2026Toulouse metro: tunnel boring machine Lise Enjalbert...Our tunnel boring machine, Lise Enjalbert, and its team have achieved a crucial milestone with the second breakthrough at the future Blagnac station. -
03.06.2026Three new service quays completed in Grand-Lahou, Côte...Our Eiffage Génie Civil Marine teams have finalized the construction of three new service quays, each measuring 20m x 12m.